EAWR 1989 & HSE GS38 SIMULATION

Safe Isolation 10-Point Lockout Drill

Safe isolation is the most critical procedure in the electrical industry. A single skipped step or wrong sequence in the AM2 or on-site can lead to immediate failure or fatal electric shock. Complete all 10 legal steps in sequence.

CIRCUIT IS ENERGIZED (230V LIVE)
Progress: 0 / 10 Steps Complete
Main Isolator · Consumer Unit RigBS 7671 / 230V AC Single Phase
100A Double Pole IsolatorControls incoming supply to installation
Point of Work Outgoing Terminals (Click 2 terminals to probe voltage):
LINE (L1 · Brown)
NEUTRAL (N · Blue)
EARTH (CPC · Green/Yellow)
GS38 Voltage Detector ReadingProbes ready
--- V
Electrician's Tool Tray & Protocols

10-Point GS38 Checklist

  • 1
    Obtain Permission & Notify
    Notify affected building occupants and client before cutting power.
    EAWR Reg 4(4)
  • 2
    Identify Source of Supply
    Accurately locate the main switch or local isolator for the circuit.
    EAWR Reg 12(1)
  • 3
    Inspect GS38 Voltage Tester
    Verify leads, shrouded probe tips (max 4mm exposed), and fused leads.
    HSE GS38 Para 7
  • 4
    Prove Tester (Before Test)
    Prove the 2-pole voltage indicator against an approved proving unit (230V).
    HSE GS38 Para 10
  • 5
    Switch OFF Isolator
    Operate the switch mechanism to isolate the incoming line conductor.
    EAWR Reg 12(1)
  • 6
    Lock Off & Secure Unique Key
    Apply lock-out padlock, attach warning notice, keep key in personal pocket.
    EAWR Reg 13
  • 7
    Test Between Conductors
    Probe Line-Neutral, Line-Earth, and Neutral-Earth at point of work.
    EAWR Reg 14
  • 8
    Confirm Zero Volts (Dead)
    Verify no residual voltage, backfeed, or shared neutral on any conductor.
    BS 7671 Reg 643.1
  • 9
    Re-Prove Tester (After Test)
    Immediately re-prove indicator against proving unit to confirm tester functioned.
    HSE GS38 Para 10
  • 10
    Safe to Commence Work
    Circuit is legally dead. Safe to handle conductors and commence work.
    EAWR Reg 14

Assessment Standard

This simulation directly matches EAWR 1989 Regulation 14, HSE Guidance Note GS38, and the NET AM2/AM2S Section A1 practical assessment marking rubric.